Mar 2018…Winter at this old house

Jan 2018…HVAC, Plumbing & Electrical started

Feb 2018…Framing inspection done started

Feb 2018…Shower installation

Apr 2018…drywall installation

Jun 2018…old floor sanding

Jul 2018…old floor finish

Jul 2018…tile floor

Aug 2018…Cabinets arrive

Sep 2018…cabinet & shelf installation

Sep 2018…Granite tops

Sep 2018…front bathroom top, Blue Bahia

Sep 2018…Back bathroom top

Oct 2018…Lights going in

Oct 2018…exterior lights

Nov 2018…Stair railing

Nov 2018…Crawl furnace fireup

Nov 2018…Rear landing

Nov 2018…backsplashes

Nov 2018…Closet shelves & rods

Dec 2018…Washer & gas dryer

Dec 2018…FINAL INSPECTIONS !!!

Dec 2018…Utility tub and custom stainless steel backsplash in the Mud Room