Cameron Street Remodel 2018
Mar 2018…Winter at this old house
Jan 2018…HVAC, Plumbing & Electrical started
Feb 2018…Framing inspection done started
Feb 2018…Shower installation
Apr 2018…drywall installation
Jun 2018…old floor sanding
Jul 2018…old floor finish
Jul 2018…tile floor
Aug 2018…Cabinets arrive
Sep 2018…cabinet & shelf installation
Sep 2018…Granite tops
Sep 2018…front bathroom top, Blue Bahia
Sep 2018…Back bathroom top
Oct 2018…Lights going in
Oct 2018…exterior lights
Nov 2018…Stair railing
Nov 2018…Crawl furnace fireup
Nov 2018…Rear landing
Nov 2018…backsplashes
Nov 2018…Closet shelves & rods
Dec 2018…Washer & gas dryer
Dec 2018…FINAL INSPECTIONS !!!
Dec 2018…Utility tub and custom stainless steel backsplash in the Mud Room